Federal appeals court dismisses application challenging Trans Mountain pipeline approval

This challenge was against the second approval

The Federal Court of Appeal has dismissed the legal challenge to Ottawa’s decision to approve the Trans Mountain pipeline expansion a second time.

In a unanimous, 3-0 decision, the court dismissed four challenges to the approval filed last summer by First Nations in British Columbia, saying in the 95-page decision that “we conclude that there is no basis for interfering” with the decision.

The decision paves the way for construction to continue on the project, though the First Nations have 60 days to appeal to the Supreme Court.

Cabinet originally approved the project, to twin the existing pipeline, in November 2016. Prime Minister Justin Trudeau said at the time it was in Canada’s national interest to build the project, which will provide oilsands producers more room to get their products to market.

That approval was overturned by the Federal Court of Appeal in August 2018, citing an insufficient consultation process with Indigenous communities and a failure to properly take into account the potential impact on marine life from additional oil tankers off the B.C. coast. Ottawa then launched another round of consultations with Indigenous communities and asked the National Energy Board to look at marine life.

In June 2019, cabinet issued its second approval for the project. Following that, the Coldwater Indian Band, Squamish Nation, Tsleil-Waututh and a group of small First Nations in the Fraser Valley asked the court to review the decision a second time. In a December hearing, their lawyers argued the government went into the new consultations having predetermined the outcome.

In their 95-page decision, the judges said that was not true.

“Contrary to the what the applicants assert, this was anything but a rubber-stamping exercise,” the decision says. “The end result was not a ratification of the earlier approval, but an approval with amended conditions flowing directly from the renewed consultations.”

The judges say the government made a genuine effort, listened to and considered concerns raised by First Nations, and sometimes agreed to accommodate those concerns, “all very much consistent with the concepts of reconciliation and the honour of the Crown.”

They also say while it is true not all the concerns raised were accommodated, “to insist on that happening is to impose a standard of perfect,” that is not required by law.

The decision says the second round of consultations did not need to start from the beginning but rather address only some specific concerns raised by the court in its 2018 decision. Today’s decision says the consultations the government held were sufficient to make their decision to approve the project reasonable.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C., with the new pipeline carrying mainly diluted bitumen for export.

It has become a political football for Trudeau as he insists Canada can continue to expand oil production and still meet its commitments to cut greenhouse gas emissions.

Trudeau’s government stepped up to buy the existing pipeline in 2018 after political opposition to the project from the B.C. government caused Kinder Morgan Canada to pull out from building the expansion. The government intends to finish the expansion and then sell both the existing pipeline and the expansion back to the private sector.

It has been in talks with some Indigenous communities about the sale but Finance Minister Bill Morneau has said the project won’t be sold until all the risks about proceeding are eliminated. Those risks include this court case.

More coming.

READ MORE: Trans Mountain begins laying Alberta pipeline for expansion

READ MORE: Landowner hearings begin for Trans Mountain expansion

READ MORE: Federal Court of Appeal to release ruling on B.C. First Nations’ pipeline challenge

The Canadian Press

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

VIA Rail lays off 1,000 unionized workers across the country

Northern B.C. route Jasper to Prince George to Prince Rupert is not affected by VIA Rail layoffs

Sunflower Highway, art initiative to connect Fraser Valley, Thompson-Nicola and Okanagan

Sunflowers made out of reclaimed materials will be installed on public art trails

Residents warned to stay away from flooded Cache Creek park

Water might look shallow, but is several feet deep in places

Ashcroft receives grants to get new hot tub and lift station

‘The hot tub is a major benefit for many residents’

Cache Creek gets funding for improvements on Old Cariboo Road

Work will help to mitigate damage from water and debris flows during flooding

B.C. sees 25 new COVID-19 cases, community exposure tracked

One death, outbreaks remain in two long-term care facilities

BREAKING: Amber Alert for two Quebec girls cancelled after bodies found

Romy Carpentier, 6, Norah Carpentier, 11, and their father, Martin Carpentier, missing since Wednesday

B.C. man prepares to be first to receive double-hand transplant in Canada

After the surgery, transplant patients face a long recovery

Grocers appear before MPs to explain decision to cut pandemic pay

Executives from three of Canada’s largest grocery chains have defended their decision to end temporary wage increases

Bringing support to Indigenous students and communities, while fulfilling a dream

Mitacs is a nonprofit organization that operates research and training programs

Northern B.C. First Nations call for reversal of grizzly bear hunting ban

Growing grizzly populations have led to fewer ungulates and increased fear of attacks says Chad Day

RCMP ‘disappointed’ by talk that race a factor in quiet Rideau Hall arrest

Corey Hurren, who is from Manitoba, is facing 22 charges

NHL’s Canadian hubs offer little economic benefit, but morale boost is valuable: experts

Games are slated to start Aug. 1 with six Canadian teams qualifying for the 24-team resumption of play

‘Made in the Cowichan Valley’ coming to a wine bottle near you

Cowichan Valley has the honour of being the first sub-GI outside of the Okanagan

Most Read