Skip to content

Work continues at Big Bar landslide as water levels remain low

Crews are working round the clock to remove debris from the site and allow passage for fish
21127710_web1_200416-ACC-Big-Bar-landslide-update-BigBarSlide_2
Crews blast a boulder at the Big Bar slide site, March 2020. (Photo credit: DFO)

Work at the Big Bar landslide site northwest of Clinton is continuing, and the COVID-19 outbreak has not caused significant delays. The Department of Fisheries and Oceans (DFO) says that prime contractor Peter Kiewit Sons ULC (Kiewit) is taking additional health and safety precautions, including tightening site access to limit the risk to workers.

The landslide response continues to be a top priority for the DFO, with resources remaining dedicated to the work. With water levels remaining low, and the addition of a swift water rescue night-shift, crews are tackling crucial in-river work around the clock. Crews recently removed additional rock from the river, installed supports for the West Bank canopy, and improved the access route in multiple locations.

Kiewit is also preparing for a second East Toe blast. Crews have detonated charges to create a plateau on the rock outcropping to use as a drilling platform. They will move an air track drill to this shelf by heavy lift helicopter in the coming days. Drilling will then commence, with a blast scheduled in April.

Since mid-January, Kiewit has made steady progress at the site despite challenging weather and difficult access. Although crews have been successful in meeting the winter work objectives, including removing large boulders and debris, recent modeling done at low water shows that a mass of slide debris situated elsewhere in the river will cause heavy flows at high water, stopping fish passage.

A team of internal and external experts has been developing contingency plans and designing alternative fish passage systems to move fish during high water, when passage will not be possible for an extended period of time. The plans include constructing a “nature-like” fishway, installing a pneumatic fish lift system, and developing a trap and transport option to collect salmon below the slide and release them upriver.

Contingency planning for the enhancement of stocks returning to the upper Fraser watershed is also ongoing. A monitoring program will be implemented throughout the salmon migration period to gather as much information as possible and to aid the implementation of the contingency plans.

DFO project staff met with Chief Roy Fletcher and Coordinator Dennis Fletcher from the High Bar First Nation on March 9, and with Chief Patrick Harry and Coordinator Catlin Duncan from the Stswecem’c Xgat’tem First Nation on March 11 to review the proposed contingency plans. DFO also discussed options and plans with representatives of the Upper Fraser Fisheries Conservation Alliance on March 11. No concerns regarding the proposed methodologies were raised during these discussions. The participants requested regular updates on next steps and their continued involvement, as all three levels of government work to reduce the slide’s impact on 2020 salmon returns and beyond.

Teams will continue to work with communities to ensure they remain an integral part of the planning, operations, and decision-making process. Sustained efforts will be required in the short- and long-term, possibly into years ahead, to reduce the impact of the landslide on future salmon stocks.

For more information about the Big Bar landslide and ongoing work at the site, please visit https://bit.ly/3bzPSar.



editorial@accjournal.ca

Like us on Facebook and follow us on Twitter